Expansion Update — June 10, 2025

Expansion Update — June 10, 2025

Our hospital expansion is transforming every day as we move steadily toward completion, with many
areas already receiving their final touches.

Tower 3rd and 4th Floors

  • Interior signage has been installed, helping to guide patients and visitors throughout the new
    facility.
  • Furniture placement continues, bringing comfort and functionality to patient rooms and
    common areas.
  • Initial clean-up efforts are underway as we prepare these spaces for occupancy.
  • The waiting areas are now substantially complete, with furniture positioned and ready for use.

Tower 2nd Floor

  • The operating suites have reached substantial completion, equipped with the latest medical
    technology to support complex surgical procedures.
  • Installation of shelving and specialized equipment for sterile processing is actively progressing.

Tower 1st Floor

  • Flooring installation on the first level is now complete, marking a major milestone.
  • Furniture for all floors has been delivered, staged, and is being carefully moved into its
    designated spaces.

Other Hospital Renovations

  • Work on the rooftop of the hospital’s new main entrance canopy continues.
  • Exterior landscaping is nearing completion, further enhancing the campus grounds.
  • Glass partitions have been installed in the registration bays, improving privacy and functionality
    for patients checking in.
  • Installation of the new entrance doors is actively underway.

Exterior Main Entrance and Drop Off  Tower Exterior July 2025  HR Reception

Office Area Cubicles  Physicians Lounge  Patient Room Head Wall

OR Suite (4)  OR Suite (1)