Tower 3rd and 4th floors
- Patient room and waiting room furniture is arriving
 - Finish installs continue, such as soap dispensers and paper towel holders
 
Tower 2nd floor
- Operating room suite, sterile processing, and central supply equipment is being installed
 - ICU rooms are nearing completion
 
Tower 1st floor
- Ceiling tile, drywall, insulation, electrical, plumbing, lighting, and HVAC duct work continues
 - Stairwell rubber treads are being installed
 
Other Hospital Renovations
- Front canopy work continues with capstone installation, sidewalks, and dirt grading preparations for landscaping
 - New patient registration by front entrance is making progress with plumbing, mechanical, HVAC and electrical installations
 - Work to prepare temporary endoscopy area continues
 
  
  
  
  
  
  
  
  

    
            
        