Expansion Update — June 10, 2025

Expansion Update — June 10, 2025

Our hospital expansion is transforming every day as we move steadily toward completion, with many areas already receiving their final touches.

Tower 3rd and 4th Floors

  • Interior signage has been installed, helping to guide patients and visitors throughout the new facility.
  • Furniture placement continues, bringing comfort and functionality to patient rooms and common areas.
  • Initial clean-up efforts are underway as we prepare these spaces for occupancy.
  • The waiting areas are now substantially complete, with furniture positioned and ready for use.

Tower 2nd Floor

  • The operating suites have reached substantial completion, equipped with the latest medical technology to support complex surgical procedures.
  • Installation of shelving and specialized equipment for sterile processing is actively progressing.

Tower 1st Floor

  • Flooring installation on the first level is now complete, marking a major milestone.
  • Furniture for all floors has been delivered, staged, and is being carefully moved into its designated spaces.

Other Hospital Renovations

  • Work on the rooftop of the hospital’s new main entrance canopy continues.
  • Exterior landscaping is nearing completion, further enhancing the campus grounds.
  • Glass partitions have been installed in the registration bays, improving privacy and functionality for patients checking in.
  • Installation of the new entrance doors is actively underway.

 